Ajaokuta Steel Company Limited.<\/a><\/p>\n<\/p>\n
In a presentation of a lecture titled: \u2018Advocacy and Activism in our Engineering DNA\u2019 a fellow of NSE, Dr. Otis Anyaeji said that the injection of N701 billion would generate N809.56 billion profit over 10 years. This, he said, averages an N80 billion profit\/year over the period.<\/p>\n
According to him, to raise the needed capital, a combination of public and private sector funds should be considered for adoption, probably on a 30:70 ratio.<\/p>\n
\u201cThis is very crucial, being another significant and consistent effort by the Nigerian Society of Engineers to further argue for ways of adding value to local resources and thereby create jobs at this difficult period.<\/p>\n
\u201cIn doing this, the investments on ground at Ajaokuta would be taken into due consideration on the public side. In other words, the real cash injection by the government may not actually be more than N100 billion at the end of the day in cash,\u201d he said.<\/p>\n
In his own remarks, the president of NSE, Tasiu Gidari-Wudil, lamented the rejection of engineering practitioners in Nigeria, wondering why a non-engineer should occupy a position meant for engineers.<\/p>\n
\u201cWe find out that engineers have been neglected in the affairs of this country. You have Minister of Communications who is very close to engineering but he is not an engineer. But why can\u2019t you bring in somebody who is from that field who will be able to deliver.<\/p>\n
\u201cSo let there be a round peg in a round hole. Let the government understand that everything about governance and politics centre on infrastructural development. You cannot get infrastructural development by neglecting engineers.<\/p>\n
\u201cIf we want this country infrastructurally, we just have to get the right people. So, the engineers must be involved. Other technologies must be involved,\u201d he said.<\/p>\n
Meanwhile, some weeks ago, the Federal Government through mediation, settled a long-standing contractual dispute with a foreign investor group in the steel industry, by securing a reduction of the total money in contention from $5.258 billion to $496 million, the Attorney-General of the Federation and Minister of Justice, Mr. Abubakar Malami, SAN, has revealed.<\/p>\n
Malami in a statement by his media aide, Dr. Umar Gwandu, yesterday, maintained that the reduction Federal Government secured from the group represented 91 per cent of the total mediation claim.<\/p>\n
He disclosed that the mediation proceedings were under the International Chamber of Commerce\u2019s, ICC, Alternative Dispute Resolution, ADR, framework, led by Mr Phillip Howell-Richardson.<\/p>\n
According to the AGF, the settlement agreement came into effect on August 19, 2022.<\/p>\n
He said: \u201cNigeria succeeded in reducing the claim in mediation brought by the international firm of King and Spalding, legal representatives of the Global group, by 91 per cent.<\/p>\n
\u201cA claim for over $10 billion was threatened in arbitration before the International Chamber of Commerce, International Court of Arbitration, Paris, in respect of five major contracts of 2004-2007 \u2013 covering steel, iron ore, and rail.<\/p>\n
\u201cIt might be recalled that the seeds of the disputes can be traced to five contracts entered into by the 1999-2007 administration that gave complete dominance over the Nigerian steel space to one company group, the Global Steel group.<\/p>\n
\u201cHowever, in 2008 a new administration proceeded to terminate these contracts contrary to legal advice supplied by the Federal Ministry of Justice, which cited the termination cost in the form of damages.\u201d<\/p>\n
The statement noted that had the then administration not terminated the Ajaokuta Share Purchase Agreement on April 1, 2008 and waited for just 55 days to terminate, it would have terminated lawfully and the government would have collected more than $26 million from Global Steel.<\/p>\n
\u201cThis was because the firm appeared unable to pay the first tranche for the Ajaokuta shares before the first anniversary of the agreement (25 May 2008).<\/p>\n
\u201cThis failure would have given Nigeria a right to over $26 million as liquidated damages under cl.12 of the Ajaokuta Share Purchase Agreement.<\/p>\n
\u201cGlobal steel, in consequence, took the FGN to the International Chamber of Commerce, International Court of Arbitration, Paris, commencing arbitration in 2008.<\/p>\n
\u201cAlthough the Federal Government negotiated a settlement in May 2013, the previous administration failed to implement its settlement agreement.\u201d<\/p>\n","protected":false},"excerpt":{"rendered":"– harps on public and private sector fubsibft Nigerian Society of Engineers (NSE) has proposed a capital injection…\n","protected":false},"author":1,"featured_media":0,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[21,2],"tags":[65],"class_list":{"0":"post-4735","1":"post","2":"type-post","3":"status-publish","4":"format-standard","6":"category-businessnews","7":"category-news","8":"tag-ajaokuta-steel-company"},"yoast_head":"\n
NSE Says Ajaokuta Steel Company Needs N701bn Work - Ebira Reporters<\/title>\n\n\n\n\n\n\n\n\n\n\n\n\n\n\n\n\n\n\n\t\n\t\n\t\n